Global Rail Australia has successfully completed a project for Australian Rail Track Corporation for the removal of mud from steel culverts and providing a new bottom concrete layer using the shotcrete process.
The scope covered culvert lining for 24 culverts at 7 different locations in the Geelong and Ararat regions of Victoria. The following activities were undertaken by Global Rail Australia in a live operational railway environment:
- Culvert cleaning
- Sand blasting
- Painting
- Installation of steel mesh
- Concreting works
All activities were fully coordinated with the client and delivered on time and to budget, aided by a fully sequenced, detailed program and Global Rail’s supervisory team. We are delighted to say that the works were completed to meet the client’s satisfaction.