Minor Track Works (Renewal & Replacement) – Pratts Bridge
CLIENT: Network Rail
DATE: Mar 2019
LOCATION: Pratts Bridge, Eridge
As part of the Sussex Region’s ongoing maintenance and renewals programme, Network Rail Works Delivery Unit (DU) engaged with Global Rail Construction Limited (GRCL) as their Principal Contractor to deliver a £100k contract for a critical sleeper renewal at Pratts Bridge near Eridge, East Sussex, 35m 1672yards.
The works required the removal of redundant 23nr PAN 8 sleepers and installation of new NRS1 base plated sleepers, ballast installation and tamping. The work was delivered as a package including planning, material management, logistics, survey and design validation, pre-works and engineering controls, delivery, and hand-back.