GRCL Secures Steel Sheet Piling Contract for BAM

Global Rail Construction Limited (GRCL), has secured a new railway civil engineering project at New Road, Welling on behalf of partner BAM. The project is located between St Johns and Crayford Creek on Network Rail’s South East Route rail infrastructure.

The core scope of GRCL’s works covers the supply and installation of 8m long steel sheet piles in order to construct a 200m long cess wall to stabilise the railway embankment. These works will be undertaken during a nine-day closure of the lines in February 2020. The full scope of works will be completed by June 2020.

Over the years, the embankment has shown signs of soil creep and localised slumping, resulted in tilted and misaligned troughing routes and ravelling of ballast from the cess shoulder onto the slope face. It is reported that the track is frequently tamped to maintain line and level. So GRCL’s scope also covers the reinstatement of the ballast shoulder and support to the cess, via the implementation of a lightweight cess support system.

Global Rail Construction are currently undertaking enabling works to prepare for their works prior the blockade. These works cover:

  • Preparation of all related Risk Assessments, Works Package Plans, Task Briefing Sheets, Programmes and Methodology statements
  • Supply, position and servicing all necessary, temporary fencing, office, welfare and ground protection for the compound on the wide payment/road

The Cess Wall Construction piling work will be commencing on 15th February 2020 and there are two follow up possessions with engineering trains to complete the Cess Walkway in May and June 2020. Works cover:

Cess Wall Construction – Blockade

  • Supply and Install 8m long steel sheet piles to construct approx 200m of cess walling, 3m from the nearest running rail on the Downline between the two LOC Staging.
  • Temporary relocation and protection of the existing S&T cables

Cess Walkway

  • Backfilling the existing cess walkway
  • Laying a new Concrete Cable Route
  • Relocating S&T cables into new troughs.
  • Fixing handrails

Global Rail Construction Limited’s civil and structural engineering capabilities take full project responsibility and offer a fully managed and integrated service for clients within the railway infrastructure.

We can provide civil and structural engineering solutions from initial project planning and design, to enabling works covering site surveys, hazard and environmental assessments, procurement, onsite construction and equipment installation, through to final commissioning.

https://www.theglobalinfrastructuregroup.com/global-rail-construction/what-we-do/civil-and-structural-engineering-and-building/

Global Rail Construction Limited’s Design Team Picks Up Award

We are delighted to announce that Global Rail Construction Limited’s design team, have been awarded a contract with Alstom covering the GRIP 4 civils design for the Swinderby Resignalling Scheme. The design programme is now underway, with Scheme Plans and Level Crossing Ground Plans due to be submitted in July and the completion of GRIP 4 in September 2020.

The team have successfully supported Alstom on a number of schemes in the past, including the Design and Build civils programme for the East Notts Modular Resignalling Scheme GRIP 5-8 works, which covered eleven Level Crossings.

The Swinderby Resignalling Scheme comprises the Resignalling and Recontrol of the Swinderby Signalling area. It will include the conversion of 4 Level Crossings and the Renewal of Swinderby Road AHB to AHB- X.

GRCL’s GRIP 4 Civil Design works will cover:

Survey

  • Non-intrusive site walkouts to areas of all works affected by scope
  • Confirmation if any local services are required to be modified/rerouted
  • Geotechnical Design/Ground Investigation report for all renewed/upgraded level crossings
  • Geotechnical assessment surveys to reduce risk of unexpected ground conditions for new signal and locations.
  • A Topographical survey of all renewed/upgraded level crossings, and a sample of REB’s, PSP, ASP, and new signal locations.
  • IBJ Surveys
  • Environmental/ecological surveys

Design

  • Provision of a Design CRE for design authority sign off
  • Civil design submissions (Forms 001/002 and 003)
  • Design Certificates
  • Details, calculations, drawings
  • AFC Designs accepted
  • Input into DRN responses
  • Design Logs
  • Designer Risk Assessments

The GRIP 4 design submissions for F001’s and F002’s will be grouped in accordance with the technical content i.e. signal bases will have their own submission, level crossing ground plans will have their own submission and at each design stage an IDC meeting will be carried out.

The design programme will be directed and managed from award to completion by the GRCL’s Design Manager. The Design Manager and Design team will be supported by Head Office resources. The team will be supported by a Ground Plan Designer, who will be embedded into the Civils Design Team. This will help to ensure that the ground plan AIP submission will have considered the necessary civils elements, eliminating the potential for issues that can occur when the design processes are separate.

Global Infrastructure Group’s design and consultancy division constantly adapts to new technology and innovation.

State-of-the-art computer-aided design and simulation systems are used to assist with analysis and design, providing significant advantages for clients by lowering project costs and reducing programmes timescales.

Our in-house activities include:

  • Civil engineering and structural design
  • Mechanical, electrical and power design
  • Telecoms design
  • CAD drafting and design including 3D modelling
  • Independent design reviews

Class 700 Signal Sighting Limitations Project

Our UK Rail Infrastructure Contractor, Global Rail Construction Limited, has been awarded a further signalling civils contract with WS Atkins at Three Bridges Station. This latest project win is hot on the heels following their recent successful delivery for the same company, covering a platform extension and associated Civils and Track (P-Way) works at Redhill Station.

The work comprises the installation of a new cantilever signal superstructure and associated transfer grillage onto 410mm steel piled foundations, the relocation of signal T280 onto a new structure and the demolition of existing structure. The scope of works also covers the installation of RA offset signal structure and installation of a raised GRP platform for maintenance access. These works will provide the required signal sighting distance for normal and turnback operation of 12-car full length units (FLU) on Platform 1

This latest success follows the introduction of the new 8-car and 12-car Class for Train Operator GTR, being enhanced by Network Rail and is to support the requirement for providing the necessary signal sighting at Three Bridges, East Croydon, Brighton and Redhill railway stations.

The location of the new T280 signal is to be moved approximately 20.5m towards London from the centre bridge abutment to behind the London End abutment and wingwall. This will permit turn-back moves of FLU Thameslink Trains towards both London and country. An area of Network Rail land has been identified as the proposed location between the abutment and wingwall of underbridge VTB3/125. The abutment front wall is reinforced concrete faced with masonry and the wing wall is masonry with concrete fill to the rear. The ground signal T1192 located on the existing T280 signal gantry will be repositioned on a new post fixed to the base of the existing signal gantry which will remain in-situ once the gantry is removed.

The lines are powered by 750V D.C. conductor rails, which extend throughout the works area. There is an existing raised GRP walkway running parallel to the siding line which steps down to track level at the London side of the proposed structure. It is proposed to install a raised GRP platform butting up against the existing raised walkway for maintenance access. There are a large amount of surface cables running out of the existing cable trough, these will need to be managed prior to construction works.

Global Rail Construction’s works will include all necessary traffic management, materials logistics and works planning and site management and will be fully controlled by GRCL’s Southern based Contract Management team.

Thameslink Metropolitan Reversible Cable Containment Works Success for GRCL

GRCL are delighted to announce the award of a Civils and E&P contract on behalf of long-term partner BAM, covering the completion of cable containment works between London Bridge and Cannon Street.

The full scope of this contract is to conclude residual works from the original Thameslink Key Output 2 (KO2), with the majority of the works being carried out in the central section inside Greater London.

The award supports the relocation of the DC feeders currently running down the West side of the Metropolitan Reversible Line between Metropolitan Junction and Cannon Street South Junction. The cables are currently surface laid and will be relocated into three newly installed GRP trough routes, by GRCL’s experienced railway civils team.

Running adjacent to the current location of the feeder cables is potentially an HV feeder cable(s) which will also require an HV assessment. This will be carried out before the main works under a line block using site warden protection. The conclusion of the resulting report may be the requirement for an HV competent person to be present during the works.

The Location of the works is in the cess to the West of the single reversible track Metropolitan Line, approximately between 01m40ch CSW to 01m45ch CSW. The Site will be accessed from Red Cross Way via the access steps between the Snowhill Lines and the Metropolitan Line. Outside of the main Week 39 works, a line block of the Metropolitan line will be required to safely access the work area.

Works will commence from 16th December 2019, when the materials will be delivered to Red Cross Way compound. During the main works, the bulk of the materials will be transported to Ewer Street RRAP and transported to the worksite using an RRV.

 

Global Rail Services Appoints Contracts Manager

Dublin based Global Rail Services Limited, has appointed Paul Connell as a Contracts Manager.

Paul will be responsible for the management of multiple project teams to ensure the safe delivery of projects on time and within budget to the stated quality and customer’s satisfaction.

Paul is a Civil Engineer by training, having studied Civil Engineering at Loughborough University, achieving a BEng (Hons) in Civil Engineering with a diploma in Industrial Studies. He then continued his personal development and in 2017 became a Chartered Civil Engineer.

Paul’s engineering experience covers a number of industries including Rail, Civil Engineering, Construction and Utilities over the past 20 years.

Prior to joining GRSL he was a Project Manager, working on various building, rail, roads, bridge, commercial and airport projects.

General Manager Tom Staunton commented on this appointment by saying:

“Paul’s all-round experience will add value to our business. His experience of the complete project lifecycle from pre-qualification and bid preparation, through to project execution and completion, will enhance our offering further.

“We all look forward to working with him.”

GRCL selected for Redhill Station Platform Extension Works

Global Rail Construction has been awarded a civils contract on behalf of WS Atkins, for a platform extension at Redhill Station.

The scope of works includes:

  • Preparation of the existing platform for installation of a new modular platform extension
  • Installation of a cable route through the platform
  • Installation of new RA (Right Away) Indicator and concrete base
  • All blockwork, tarmac and necessary works to existing copers
  • Slotted sleeper installations and IBJ (Insulated Block Joints) recoveries and renewals

The project is being delivered on key weekends commencing in week 29 and also during mid-week nights.

This project is part of the new 8 and 12 car Class 700 programme for Train Operator GTR, being enhanced by Network Rail and is to support the requirement for providing the necessary signal sighting at Three Bridges, East Croydon, Brighton and Redhill railway stations.

The works will include all necessary logistics and planning management and will be fully controlled by GRCL’s project management team.

Aidan Kelly Promoted to MEP Director at Global Rail Services

Global Rail Services Limited (GRSL) is pleased to confirm the promotion of Aidan Kelly to MEP Director. The Rail and Infrastructure contracting specialist which delivers the design and project management of these specialist services, is delighted with this appointment. It is full testament to the commitment and passion that Aidan has provided during a career which spans over twenty years in the Mechanical, Electrical & Power sector.

His role going forward, will involve autonomously running our in-house MEP Division -a core competency within the company – whilst liaising with the other business divisional Directors.

Whilst an ability to bring in additional business is always welcome; the role will concentrate on growing further and developing the existing engineering capability of the organisation with a competent and efficient in-house MEP team, delivering cost effective solutions to the various existing and new projects.

Ivan Holloway, CEO of Global Rail Services also added:

“Aidan is a qualified professional with suitable certifications and accreditation to reflect his seniority in the industry and has spent a number of successful years with us, supporting the management and delivery of Mechanical, Electrical & Power works for our customers. This new role is well deserved, and we look forward to him to developing our MEP offering substantially over the coming years.”

GRSL are deployed on a wide range of rail, utilities and energy projects including:

  • Commercial and industrial
  • Private domestic
  • Bespoke installations
  • Site enabling field works
  • Fibre splicing & copper jointing
  • Clean earth systems
  • Telecom and signalling room fit outs
  • Electrical maintenance
  • Access and security systems including CCTV
  • Fire alarms
  • Lighting control systems
  • Building management & control

UK’s GRCL Partners Up with Hedson Rail for Track Works on Wessex

Our UK Rail business, Global Rail Construction Limited and Hedson Rail Limited have formed a strategic partnership, to successfully secure Phase 2 of the Track Delivery work bank on behalf of Network Rail’s Works Delivery team on the Wessex Route.

The contract will see both companies working together to deliver track maintenance and renewals works, initially between October 2019 and April 2020 on one of the UK’s busiest rail routes. Global Rail Construction will be acting as programme manager for the works, with Hedson Rail delivering the responsible engineering and technical requirements.

The works programme, which specifically covers Heavy, Medium and Light Plain Line and S&C Track Refurbishment and Re-Railing, will see the team working in locations throughout the Wessex Route which runs from South-West London as well as from London Waterloo to the South and South-West of England taking in all or part of the counties of Surrey, Berkshire, Hampshire, Dorset, Somerset and Wiltshire.

This is not the first time the businesses have worked together, with successful track works already completed in the South East – this burgeoning partnership is something that both businesses are very proud of.

GRCL’s UK MD Marco Lombardelli summarised this further, saying:

“As a business, we are always looking to increase our opportunities and saw this as the perfect target. We are delighted therefore, that our programme management capabilities coupled with Hedson Rail specific track engineering and site delivery capabilities were seen as the right solution for Network Rail.

We believe that the right partnerships can add enormous value and will continue to develop existing and seek out future strategic partners, in order to grow our capabilities. We are delighted to add a track arm in conjunction with Hedson Rail to our UK offering, which now aligns our model with the worldwide offering that can be found in both our Irish and Australian businesses.

We are able to design, build and execute a full multi-disciplinary track project by adding Track, to our existing and established successful offerings in Civil Engineering and Building, Power and Signalling.

I am pleased with this new contract and send a thank you to the team who helped make this possible.”

Martin Hedley, MD of Hedson Rail also added:

“Delivering track projects in Wessex and the South East has been a strategic target for Hedson Rail for some time and we are delighted to have formed the partnership with GRCL to make this possible. We are a local business that know the Wessex route well and in collaboration with Network Rail Works Delivery, we have absolute confidence in our team to successfully deliver the challenging work bank.”

Another Successful Milestone Achieved by Global Rail Services at Limerick Junction

Global Rail Services have had another successful weekend working on its contract for Irish Rail, constructing the new Limerick Junction Down Platform and Footbridge Works

The team has successfully completed its latest contract milestone, by completing the assembly and installation of all steelwork for the new footbridge.

The works were undertaken between 12th and 23rd August 2019, utilising a combination of normal daytime working hours within a green zone and midweek night-time possession working hours between 11pm and 5am – all in agreement with Irish Rail.

The works included a number of carefully planned stages which included:

  1. Site Set Up
  • All plant set up in advance of the works within the confines of the site perimeter in a green zone. A large zone for working was built and fenced at the back of the of the new down platform and the new tracks have been ballasted out to allow access up the new platform.
  1. Delivery and assembly of the Structural Steel Footbridge
  • All pre galvanized, pre painted structural steel, mesh panels, handrails, stainless steel items for the new bridge frame delivered into the green zone and carefully unloaded with the GRS teleported and stacked for assembly
  • The main bridge portal placed onto a prefabricated temp support frame and bolted into position. When all portal frames were in place all supports and braces were placed and secured into their final position in line with the AFC Fabrication drawings.
  • On completion of the steel support frame the Woven Wire mesh panels were placed and aligned into the required position and secured with SS SHS sections and 60x5mm flat as per the AFC drawings.
  • The entire section for the footbridge was completed and checked against the existing sleeves on the footbridge and confirmed that the structure fits when lifted into position in line with the AFC drawings
  • Horizontal Ties were installed across each portal frame to support the frame during lifting.
  1. Stair Steel Assembly
  • Anchor bolts were installed into the side of the stairs to the required centres utilising a small MEWP placed on the platform behind fencing within a green zone.
  • Drilling holes within a green zone with the exception of the Cork line side of the up platform, which was completed under possession as this section of platform is live during the day. GRSL made every effort to pre-drill as much as possible within a green zone environment to speed up the possession works.
  • The stairs steel frame units which consist of 2 nr uprights and 1 nr cross member were assembled on the ground in line with the AFC drawings.
  1. Main Bridge and Up Platform Stairs
  • The main bridge steel and the up-platform stairs steel, were then installed under possession with a 90t crane
  • The bridge steel on the down platform was installed and placed from the back of the platform with the aid of the GRS teleporter. Each frame was lifted and guided into position by our team from Hyland Engineering, with slings onto pre-drilled bolts to the required line and level. Once in position each frame was bolted and secured into its final position
  • Each frame was then connected with the horizontal running beams as per the AFC drawings. All beams were lined up and bolted into position
  1. Installation of Handrails and Woven wire mesh to stairs
  • All materials were placed onto the platform with the teleporter and carried across the footbridge and stairs to their final position in a green zone
  • All Woven Wire mesh panels were then placed and aligned into the required position and secured with SS SHS sections and 60x5mm flat as per the AFC drawings.
  1. Installation of Avigilon IP camera system on stairwells and footbridge
  • Avigilon IP cameras were installed onto the steel work of the new footbridge and stairwells to capture and record 360° video footage 24hrs a day
  • Steel conduit was installed onto the steel work from the newly built service rooms under each stairwell, up to the location of each IP camera.
  • A CAT5 network cable was installed via newly installed conduit, from the new IP Network switch in service rooms to the IP cameras
  • All IP cameras were tested from the from the station controller’s office and images agreed by Irish rail
  1. Installation of lighting system on stairwells and footbridge
  • Once the steel work of the bridge arrived on site it was examined, a few proposals were put forward for the best and neatest way of installing the cabling for the proposed luminaires.
  • An installation design and method was agreed before the steelwork was erected.
  • Once the steel work was installed the electricians worked on all sections of the stairwells and footbridge at the one time
  • MEWPs and ladders were used for height access
  • Steel conduit was installed from the newly installed service rooms under stairwells up to the steel work of the stairwells and footbridge
  • 03No of lighting circuits were installed from the newly installed distribution boards in service rooms under stairwells, up to the proposed luminaires
  • These lighting circuits were wired with four core 2.5mmsq Silflex cable
  • This Silflex cable was installed via the box section of the steel work and the newly installed steel conduit
  • The luminaires were installed into position as per AFC drawings
  • All luminaires were terminated and tested as to ETCI regulations

On completion of this milestone, the works were successfully inspected and signed off by Irish Rail.

Global Rail Services are managing and delivering these works as part of a new €2.5m project at Limerick Junction on behalf of Irish Rail. The overall objective via the implementation of this scheme is to deliver improved journey times and provide timetable enhancements on the Dublin-Cork and Dublin-Limerick lines, which are currently restricted by a platform conflict at Limerick Junction.

A big thanks to all involved for their dedication to ensure the safe and successful completion of another important project milestone.

Richmond to Gunnersbury D&B Civils Completion

UK Rail Infrastructure Contractor, Global Rail Construction Limited (GRCL) has completed 4000m of TTS troughing installation works on the LUL Network between Richmond to Gunnersbury on behalf of BAM.

Having already successfully completed the Design works for this Cable Route Management System route as part of a separate contract with BAM, this contract completion highlights the strength of Global Rail Construction Limited’s (GRCL’s) integrated end to end, in-house Design and Construct capabilities.

These works form part of the wider modernisation and up-grading the Sub-Surface Railway network, comprising of the Metropolitan, District, Circle and Hammersmith & City Lines, whereby Network Rail is required to design and build new Cable Route Management Systems to support primary Power/Signal cables from Turnham Green to Richmond.

Operations Director, Sean Donaghey added:

“Very pleased with the completion of this important contract. We look forward to working with our long-term partner BAM again soon.”

GRCL offer rail infrastructure contracting services on a design and construct basis. Our capabilities support the latest technology, management and engineering know-how, which allow us to deliver high profile projects throughout the UK rail network on both Transport for London and Network Rail infrastructures.